South Harbor dredging going slow but steady

View Discussion

https://www.petersburgpilot.com/story/2023/01/26/dockside/south-harbor-dredging-going-slow-but-steady/12802.html

The South Harbor dredging is continuing to make progress as crews dig their way to the shore, having removed approximately 13,000 cubic yards of material as of Monday according to Harbormaster Glo Wollen. Western Marine is undertaking the project, which is being overseen by the U.S. Army Corps of Engineers, and plans to dredge a total of 83,000 cub...